Chapter 1:
India’s power generation capacity additions
In this chapter
Momentum in renewable additions keeps India on course for 2032 targets
India is broadly on track to meet the National Electricity Plan (NEP) 2032 capacity mix: solar is scaling fast, hydro is likely to meet or exceed its target, and coal capacity has a strong pipeline of projects. Wind must accelerate—especially onshore—to align with targets. Nuclear remains the most uncertain due to long build times and a limited near-term pipeline.
India is experiencing record renewable energy expansion, with solar leading through 20+ gigawatts (GW) of annual additions and strong distributed deployment. This makes the NEP 2032 target of 365 GW attainable despite possible bottlenecks. Wind additions need to accelerate significantly to meet targets, while large hydro is on track to slightly exceed its goal. Coal capacity will easily reach NEP targets, but nuclear is set to miss its mark due to slow project initiation and construction.
Crucially, battery storage is rapidly expanding, with a robust project pipeline making the ambitious 236 gigawatt-hours (GWh) NEP target achievable, while pumped hydro storage is near its goal with substantial projects under execution and investigation, ensuring critical support for renewables integration.
1.1
20 GW+ annual addition is becoming the new norm for solar
India is witnessing an unprecedented surge in solar capacity additions. The fiscal year (FY) 2024–25 alone saw a record 23.8 GW of new installations — the highest ever. The momentum continued into FY 2025–26, with another 22 GW already commissioned within half a year, (untilSeptember 2025). This rapid build-out reflects several converging factors: the scale and competitive pricing of renewable energy auctions held in previous years, the rush among developers to complete projects before the inter-state transmission (ISTS) waiver begins to taper, and the strong response of a market that has matured with remarkable speed.
Solar photovoltaic (PV) has short lead times, so capacity planned for 2032 could still begin development as late as 2030. India already has 116 GW installed and 86 GW under construction. To reach the NEP target of 365 GW, the country needs an additional 163 GW, averaging 32.6 GW annually through 2030. Crucially, this growth will not only come from large-scale parks but also from distributed deployment in the residential and agricultural sectors.
The government has announced ambitious plans for rooftop and agri-solar under the Pradhan Mantri Kisan Urja Suraksha evam Utthan Mahabhiyan (PM-KUSUM) scheme and other state schemes. These could provide a significant share of the incremental capacity. Combined with ~30 GW of hybrid solar–wind projects in the pipeline, the NEP target looks achievable, though land, grid and financing bottlenecks could still pose risks.
1.2
Onshore wind capacity additions need to accelerate, with the enabling conditions already in place
India’s wind growth will be affected by both demand- and supply-side forces. There is a demand for much higher additions of wind in India. States’ resource-adequacy assessments point to about 100 GW of wind needed by 2030 to maintain reliability, underscoring wind’s role in the generation mix. Corporate and industrial decarbonisation goals, coupled with rising interest in round-the-clock (RTC) and peak-power products, are strengthening offtake. Wind’s complementarity with solar—especially its evening output—helps meet peak demand and lowers the delivered cost of RTC supply. Wind has also earned higher evening capture prices in wholesale markets, reducing merchant risk for IPPs.
On the supply side, India’s manufacturing capacity and strong resource base provide a solid foundation, and scaling installations to 8–15 GW per year could trim costs by ~10–20% through economies of scale.
Taken together, the ingredients for rapid growth are in place. Converting them into outcomes will hinge on timely grid build-out, stable policies, and smooth conversion of auction awards into bankable power purchase agreements (PPAs).
Since onshore wind typically takes about two years to build, projects entering the pipeline as late as 2030 can still support the 2032 target. As of now, India has 52 GW installed and 28 GW under construction (80 GW total) against an NEP target of 124 GW by 2032, leaving a 44 GW gap—implying average additions of roughly 8.8 GW per year over 2026–2030 (versus ~3.5 GW added in 2024).
1.3
Hydro is set to meet or slightly exceed its NEP target
Hydro growth has been slow in recent years, and the NEP adopts a conservative stance, but the drivers for acceleration are in place.
There is a lot of policy support for large hydro, e.g. budgetary support is available for flood-moderation and enabling infrastructure and mandates for hydropower purchase obligations (HPOs) for distribution companies.
In terms of the demand side driver, hydro is likely to play a critical role in grid stability and flexibility, helping to balance the increasing share of variable renewables such as solar and wind. Its ability to provide peaking power, frequency regulation, and ancillary services is central to India’s evolving grid needs.
On the market side, the rising demand for firm and flexible power is boosting hydropower’s relevance. Hydro’s dispatchability and low marginal cost make it a competitive and reliable complement to variable renewables.
In terms of resource availability, India’s large untapped hydro potential—especially in the Northeast—remains a long-term growth driver, with a planned program to evacuate about 76 GW from hydropower projects in the Brahmaputra basin.
The constraint is time: large reservoir projects typically need 5–7 years. Therefore, to count for 2032, projects must already have been in the pipeline by the mid-2020s. Today, India has about 54 GW installed and 13 GW under construction, keeping the ~62 GW NEP-2032 target within reach if execution stays on schedule.
1.4
Coal is set to achieve its NEP 2032 capacity goal
Coal will continue to anchor India’s power system this decade, with a large pipeline already under execution and more units scheduled to commission steadily between FY 2025-26 and FY 2029-30. As of August 2025, India had ~217 GW of coal and 6.6 GW of lignite installed, with ~35 GW of new supercritical (SC)/ultra-supercritical (USC) coal plants under construction across 25 projects. These are predominantly in the central and state sectors. In FY 2025–26, alone India targets ~10 GW of thermal additions, and multiple units (e.g., Khurja, Buxar, Ghatampur, Patratu, Yadadri) are slated for trial runs/commissioning, with further blocks (Lara-II, Talcher-III, Sipat-III, Singrauli-III, Nabinagar-II, Talabira) stretching into 2027–30.
The near-term drivers are clear: (i) peak-demand growth and resource-adequacy needs, (ii) coal fleet replacements with higher-efficiency USC units, and (iii) firm capacity to complement fast-rising solar.
India’s coal programme also benefits from defined fuel linkages for most central/state builds and ongoing transmission tie-ins (e.g., 400/765 kilovolt (kV) evacuations listed for each project).
At the same time, execution risks persist: site and land hold-ups, rail siding readiness, ash dyke construction, BoP (balance-of-plant) bottlenecks (CHP/AHP or coal-handling plant/ash-handling plant), EPC (engineering, procurement and construction) mobilisation gaps, and transmission synchronisation can—and do—push schedules. The Central Electricity Authority (CEA)notes slippages at projects such as Talcher-III, Patratu and Buxar.
Overall, with ~35 GW already in the ground and staggered commercial operation dates (CODs) through 2030, coal remains well-positioned to meet the NEP-2032 mix requirement, provided grid evacuation and last-mile BoP works keep pace.
1.5
Nuclear is likely to fall slightly short of the NEP target
India is positioning nuclear as a strategic pillar of its long-term transition. The Union Budget 2025–26 targeted 100 GW by 2047 and seeded the Nuclear Energy Mission with ~ USD 2.4 billion for small modular reactors (SMR) R&D (at least five indigenous SMRs by 2033), alongside planned amendments to the Atomic Energy Act and Civil Liability for Nuclear Damage Act by 2026–27 to enable greater private participation and a clearer liability regime.
Near-term capacity is set to rise through a pipeline of Pressurised Heavy Water Reactor (PHWRs) (including fleet-mode 700 megawatt equivalent (MWe) units), ongoing JV models (e.g., Nuclear Power Corporation of India Limited (NPCIL)–NTPC), and in-principle large project approvals. Parallel thrusts on localising the value chain, leveraging thorium, and bilateral technology cooperation (including SMRs) aim to accelerate diffusion and reduce import risk.
The medium-term growth thesis rests on three enablers: (i) policy and market design—stable offtake frameworks, viability funding and market guarantees for first-of-a-kind projects; (ii) technology pathways—Bharat Small Reactors (BSRs)/PHWRs for industrial captive loads and grid-connected baseload, plus SMRs to repower retiring coal sites and serve remote demand; and (iii) capability build-out—domestic manufacturing, fuel security (including new uranium finds and closed-fuel-cycle progress), and internationally benchmarked safety.
Execution risks are material. Nuclear faces long lead times, cost and financing hurdles (especially for SMRs), exposure to geopolitical/geoeconomic uncertainty, competition from storage-integrated renewables, potential mismatch with flexible grid needs, sizable public support requirements, and cyber/kinetic security considerations. Even with momentum, achieving 100 GW by 2047 implies more than 4 GW average annual additions for two decades—well above India’s historical pace—so timelines may slip without sustained reforms and bankable project structures.
To contribute to the 2032 targets, any new nuclear projects must already be in the pipeline by 2022–2026. India has 8.8 GW installed and 6.6 GW under construction, needing another ~5 GW to reach the 20 GW target. Around 7 GW is in the pre-project phase, but these are unlikely to add to the capacity in 2032.
1.6
Strong storage surge makes NEP target attainable
Battery energy storage systems (BESS) and pumped hydro storage (PHS) are the backbone of the next phase of India’s transition—smoothening the solar midday trough, covering evening ramps, and providing reserves and contingency support.
The growth of storage will impact the growth of renewables, particularly solar. Utility-scale BESS can typically be built and commissioned in 6–18 months, meaning capacity tendered in FY 2026–28 can still be online well before FY 2031–32. By contrast, pumped hydro usually requires around 8 years to deliver, given land, water, tunnelling and environmental clearances. This makes storage the fastest lever to convert India’s growing solar and wind into dependable evening and peak supply.
Batteries provide essential flexibility for the system (e.g., second-by-second balancing, and inertia support from grid-forming inverters) and increasingly offer large bulk storage. There are many batteries globally now installed with 8 hours of storage, which comes close to helping solar and battery alone meet the demand profile of a consumer.
While only 500 megawatt-hours (MWh) is operational as of August 2025, India’s battery storage pipeline is sizable, with ~68 GWh across stages. A little less than 10 GWh is under construction. An additional ~38 GWh is in the tendering or bidding stage. A further ~20.35 GWh has been awarded. If these projects materialise, the total will be around 68 GWh. Some tenders have been cancelled as well. Thirty tenders representing ~7.22 GWh, or 9-10% of all BESS capacity ever announced, were cancelled. Since most of this growth happened in the last two years, achieving the NEP target of 236 GWh seems achievable.
As of August 2025, India has 6.7 GW of pumped storage operational with Pinnapuram and partial Tehri PSS online and 12.11 GW under construction, plus about 7.1 GW at the detailed project report (DPR) or pre-construction stage. This brings the executable subtotal to roughly 25.91 GW, which is very close to the NEP target of 26.7 GW. With around 61 GW in survey and investigation, the growth potential is strong.