Load shifting is limited because most data centre workloads cannot easily be moved to different times. An alternative is to keep workloads running while switching their electricity source from the grid to the data centre’s own generation or storage, where these can be built. Many developers are already pursuing this option in response to multi-year waiting times for a grid connection.
Nowhere is this trend more visible than in Texas. The state is set to overtake Virginia as the largest data centre market in the US. Meanwhile, its grid operator, ERCOT, faces almost 400 GW of connection requests from data centres, nearly five times the state’s record peak demand of 85.5 GW. In response to this queue, developers have announced 40 GW of onsite generation for data centres in Texas.
Onsite generation could take significant pressure off the grid, but the benefits and risks depend on what is built behind-the-meter. This chapter uses two Texas data centres to estimate how much grid relief onsite generation could offer compared with load shifting, then looks at what would be needed to deliver that relief from clean sources.
Switching to onsite generation would provide almost five times more grid relief than load shifting
The two data centres, Stargate Abilene and Comanche Circle, are both expected to have an ERCOT grid connection and onsite generation. Together they represent about 5.6 GW of new load due online by 2030. At the typical US data centre utilisation rate of 48%, they would draw about 2.7 GW on average and likely more, as AI-specific facilities tend to run at higher utilisation.
Using the same assumptions as Section 2.1, load shifting at these facilities could relieve an estimated 0.55 GW during a grid stress event. Switching to onsite generation could reduce grid demand up to 2.7 GW, almost five times as much, without changing how the data centres operate. Against ERCOT’s projected 2030 peak demand, this is the difference between relieving 0.4% of peak demand and 2%.
From a grid perspective, switching to onsite generation offers greater potential to reduce demand at peak times, although it needs careful coordination. If many facilities switch to batteries or backup generation at the same time during a grid disturbance, the sudden drop in demand could itself affect system stability.
Switching also appears to be the data centre sector’s preferred route. In Ireland, the energy regulator initially proposed mandatory flexibility requirements for data centres. Following public consultation, these were replaced by requirements to provide generation or storage, now mandatory for data centres of 10 MW and above.
The risks of onsite generation could be turned into an opportunity for a more cost-efficient power system
Without appropriate regulation, onsite generation carries two risks. The first is fossil lock-in: as the US trend shows, developers seeking reliable power are turning to gas even as grids decarbonise, and uncertainty over future data centre growth adds the risk of stranded assets.
The second is paying twice for the same generation capacity. As power demand grows, grid operators seek to secure additional firm generation capacity to ensure system reliability, often through capacity auctions. Many data centres are seeking a grid connection while also building onsite capacity. If grid operators do not count the onsite generation a data centre already has, they risk contracting additional capacity to cover load that could largely supply itself at peak as two sets of assets would be built for the same load – with the cost of the grid-side generation capacity shared by all consumers, not just the data centre. These are not insignificant costs: in the capacity auction organised by PJM, the largest regional grid operator in the US, for the years 2028-2029, data centre load alone was responsible for $6.3 billion of the $16.4 billion in capacity charges.
The US pattern is not inevitable. In Malaysia, developers are pairing new data centres with large clean power projects. DayOne Data Centres has signed agreements for around 1.5 GW of solar and 2.2 GWh of battery storage to supply its Malaysian operations, and is exploring up to 1.5 GW of onsite generation and storage with national utility Tenaga Nasional Berhad (TNB).
Overbuilding can be avoided too. One of the few available studies modelled six large US data centre sites combining onsite resources with a flexible grid connection. Grid power remained available for more than 99% of hours, with onsite resources needed for only 40–70 hours a year. By using their own capacity only when needed, data centres can reduce the need for new system build and shift costs of meeting their demand onto themselves onto the data centre, substantially lowering the costs that fall on other consumers. Whether onsite generation benefits or harms the wider system therefore depends on how it is regulated.