Delhi, 25 February 2025 – India’s power sector transition requires a significant increase in financing, with annual investment flows needing to grow to USD 68 billion by 2032 to meet the National Electricity Plan (NEP-14) targets and achieve India’s 500 GW renewable energy goal by 2030—requiring a 20% compounded annual increase from current levels.
A new report from Ember maps various financial risks associated with renewable projects. Based on the assessment of these risks, it estimates the premiums associated with these risks and the overall impact of the risks on the cost of capital.The report moves beyond traditional “thumb rules” for calculating risk premiums by adopting a data- and modeling-driven methodology instead.
Project commissioning delays and uncertainties due to specific characteristics of new age -Firm and Dispatchable Renewable Energy (FDRE) projects are expected to have the greatest impact on the cost of capital.The analysis suggests that risks due to a combination of both could increase the cost of capital by up to 400 basis points.
Commissioning delays have been caused by land acquisition bottlenecks, grid connectivity delays, and delays in power purchase agreement (PPA) signing. These delays have averaged 17 months, with projects in some cases extending even up to 26 months and beyond.